After notification by the code official, an application for a permit shall be considered abandoned after how many months?

  1. 3 Months

  2. 4 Months

  3. 6 Months

  4. 12 Months

The correct answer is: 6 Months

In Virginia, the timeframe for an application for a permit to be considered abandoned after notification by the code official is established as six months. This time period is significant as it provides applicants with a reasonably ample opportunity to address any issues or requirements that may have caused a delay in the processing of their permit application. This policy ensures that applicants are motivated to respond and complete their applications in a timely manner, while also allowing the permitting authorities to manage their workload effectively and avoid backlogs caused by long-standing open applications. Thus, the six-month period strikes a balance between giving applicants enough time and maintaining the efficiency of the permitting process.