What formula is used to calculate the bid price?

  1. (Dir Cost * 100) / (100 - %)

  2. (Total Cost - Overhead) / Total Revenue

  3. (Total Revenue - Expenses) / Total Revenue

  4. (Total Assets - Total Liabilities) / Total Equity

The correct answer is: (Dir Cost * 100) / (100 - %)

The formula for calculating the bid price, represented as (Direct Cost * 100) / (100 - %), is widely utilized in contracting to ensure that the bid is competitive while accounting for necessary profit margins. In construction and contracting, direct costs refer to expenses directly attributable to the project, such as labor, materials, and equipment. The percentage in this formula typically represents the desired profit margin or markup. When calculating the bid price, it is crucial to ensure that the final bid adequately covers all direct costs and includes a profit margin that aligns with business goals. This formula facilitates the determination of the total bid price by adjusting the direct costs in relation to the planned profit margin. Using this method ensures that bids remain financially viable while being competitive in the marketplace. The alternative formulas provided in the other options relate to different financial metrics or calculations. For instance, they focus on various aspects of revenue, expenses, assets, and equity that do not directly pertain to the specific context of calculating bid prices in contracting. Thus, they do not serve the specific need for establishing a bid price where direct costs and profit margins are the primary concern.